CERTIFICATE OF SUBSTANTIAL COMPLETION
Name of Project:
Contractor:
CPB Project #:
Phase
Address:
Project:
Location:
Contract No.:
Contract Work:
SUBSTANTIAL COMPLETION DATE:
Complete
Partial -
Substantial Completion and warranty time periods affected are defined in the General Conditions of the Contract. All parties listed
below have reviewed the work under this Contract and recommend issuance of the substantial completion. The
________________ (Owner) concurs with NMED's acceptance of the A/E's certification, will assume full possession and
responsibility for the project or designated area, less punch list items, on the above listed Date. All warranties will start the day of
substantial completion, with the exception of those items on the punch list, which will start on the date of Final Acceptance. The
responsibility of the Contractor for heat, light, other utilities and Builders' Risk Insurance required by the Contract ceases at
Substantial Completion. Other required insurance remains the Contractor's responsibility until the Certificate of Final Acceptance
is issued.
PUNCH LIST: N/A
A list of items to be completed or corrected, prepared by the Architect/Engineer, checked and augmented as required by the Prime
Contractor or Construction Manager is appended hereto. The failure to include any item on such list does not relieve the
Contractor of the responsibility to complete all work in accordance with the Contract documents.
The Contractor shall complete or correct the work on the punch list appended hereto by
/
/
. The punch list consists of
items.
Mo. Day Year
Representative
Contractor
Date
Representative
Coordinating Contractor
Date
Representative
Architect/Engineer
Date
Community Name
Representative
Date
CPB Project Manager
Date