Contractor’s Weekly EHS Report
Instructions:
This form is to be completed at the end of each week that work is performed by a contractor on SURF property. The form is to be
turned in, with all of the pertinent attachments, to the SURF POC by Tuesday of the following week.
Fill in the top portion of the form with the requested information. List all subcontractors that worked on the project during the week
being reported.
List all attachments that accompany this form. The following is a list of possible required attachments.
New and Revised JHAs:
Confined Space Entry Permits
Weekly Inspection Form
Toolbox Talk with Attendance Roster
Hot Work Permits
First Report of Injury/Incident
Excavation Permits
Incident Data Collection Form
Daily Trenching Log
Investigation Reports
Mobile Equipment Inspections
Personal Sampling Results
LOTO Documentation
Site Orientation Documentation for New Workers
First Aid Log if New Entries Have Been Made
Report all major activities completed to include EHS activities
Report the number of OSHA recordable injuries occurring during the week with a brief description of each and attach a copy of the
First Report of Injury/Incident Form, Incident Data Collection Form, and any Tap Root, or other investigation documents. The
originals documents must be turned in within the following timeframes as specified in the CEHS Manual and copies included with this
report.
Initial Report
As soon as the scene is stabilized (but not more than 1 hour)
First Report of Injury/Incident Form
By the end of shift
Preliminary Investigation Report
24 Hours
Detailed Investigation Report
4 Days
Report any First Aid cases or Near Misses reported to you either verbally or in writing to include those reported on the 5-point cards.
Report all Environmental releases
Contractors are required to do a documented self inspection at least once each week. Report the findings from that inspection and any
other inspections conducted and the resolution of those findings. Attach a copy of the inspection form to this report.