DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
3
Terminal 4 Wheeler Bay Shore Line Restoration
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers Inc.
Date:
October 5, 2010
Jeff Hargens, Project Manager
Day:
Tuesday
Contractor’s Rep./Title:
Overcast-Sunny, Dry,
50
68
slight breeze, no dust
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
T4 Wheeler Bay Shore Line Restoration
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
1-Hitachi 160 track hoe
Tim Stone, Anchor, Port Inspector
1-CAT IT28G front loader
3-steel sheets
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
Moving delivered rip rap to work area from 0-30 to 0+75, approximately.
Work Completed:
13 loads of rip rap were delivered to the site (total of 190.28 tons)
3 loads of select fill was delivered by truck and transfer (total of 6 loads and 97 tons)
Repaired demarcation fencing where it had been washed away or torn.
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors:
Jeff Hargens, NEI.
Notes:
Kinder Morgan will be back to work tomorrow and using the rail line.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA