Daily Observation Report Page 30

ADVERTISEMENT

DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
14
Wheeler Bay Shoreline Stabilization Slope Repair
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers
Date:
October 25, 2010
Jeff Hargens, Project Manager
Day:
Monday
Contractor’s Rep./Title:
48
51
Good
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
Terminal 4, Wheeler Bay bank stabilization
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson (NEI); Mike (NEI); Tim Stone (Anchor)
1 Hitachi 160 track hoe; 1 CAT IT28G front loader; 1 NEI support
Mike Roper/Jeremy Haines (NEI)
truck
John Casterly and 5-man crew (Casterly Landscaping)
1 landscapers support truck with horse trailer containing plants
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
Began work at approximately 07:30; silt fence damaged over weekend due to heavy rain; continued driving wooden stakes into
fabric; began chaining large woody debris to anchor bolts; landscaping crew arrived at about 10:30 and began planting at the south
end of project; continued rip rapping; I left site at about 14:30.
Work Completed:
Repaired silt fence, completed driving wooden stakes through fabric at north end of project; chained woody debris to anchor cables
at north end of project; landscaping crew began planting plants at south end of project; NEI completed rip rap along base of access
road between top of bank and shoreline, and placed select fill material above top edge of rip rap.
Discrepancies Noted: (Nonconformance Report #_____)
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors: Roger Anderson, Kelly Madalinski and Marcel Hermans (POP); Jeff Hargens (NEI)
Notes:
Attended Monday construction meeting.
John Howland, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA