DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
2
Wheeler Bay Shoreline Stabilization Slope Repair
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers, Inc.
Date:
October 4, 2010
Jeff Hargens, Project Manager
Day:
Monday
Contractor’s Rep./Title:
Overcast, partly sunny,
55
65
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
drizzly, cool
Location and Type of Work:
Terminal 4, Wheeler Bay
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
Mike Madison, NEI
1-Hitachi 160 Track hoe, 2-NEI work trucks
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
No new work was started.
Work Completed:
Completed removing all woody debris out of work area, removed existing habitat layer and exposing underlying rip rap.
Discrepancies Noted: (Nonconformance Report #_____)
Discussions with Contractor (include orders given and received):
Kinder Morgan will not be operating the rail line tomorrow so NEI will be bringing in half of the required rip rap and some select fill.
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors: Kelly Madalinski, POP; stopped by the site. Jeff Hargens, NEI; stopped by the site after contractors meeting.
Tim Stone on site as Port Inspector.
Notes:
Weekly construction meeting; Roger Anderson, POP; Kelly Madalinski, POP; John Durst, POP; Marcel Hermans, POP; Ingmar
Saul, PMX; Tim Stone, Anchor; John Verduin, Anchor, by phone.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA