DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
12
Terminal 4 Wheeler Bay Shore Line Restoration
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers Inc.
Date:
October 21, 2010
Jeff Hargens, Project Manager
Day:
Thursday
Contractor’s Rep./Title:
50
60
Partly Sunny, Dry,
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
T4 Wheeler Bay Shore Line Restoration
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
1-Hitachi 160 track hoe
1-NEI work truck
Mike Madison, NEI
1-CAT IT28G front loader
Tim Stone, Anchor, Port Inspector
4-steel sheets
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
Driving pilot holes for the Manta Ray anchors starting at 0-10 to 1+00. Completed 12 pilot holes.
Work Completed:
2 truck and transfer loads of top soil were delivered for 50 yards.
Completed coir fabric and topsoil repair from 3+50 to 7+00 at approximately the 16 foot elevation.
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors:
Jeff Hargens, NEI; John Howland, PMX; John Durst, POP; Philipp Bails, POP;
Notes:
The contractor did not work on Wednesday 10/20.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA